In this section:

Sardinia Paper 2007

GO

Mondi - Unique Geomembrane Lining Design

GO

Aquatan Supervisors receive Master Seamer certification

GO

Enhanced Barrier System 

GO

Environmental impact of waste-landfill sites

GO

CE-marking for GSE Geomembranes

GO

Gigsa Biannual Award

GO

Earthworks and first installation of GCL

HDPE liner installation

R-fPP cover installation

Molasses floating cover reservoir at commissioning

 news

MOTIVATION FOR NOMINATION FOR GIGSA BIANNUAL AWARD

Aquatan and Jarrod Ball and Associates received the "Award for the Excellent Use of Geosynthetic Materials in Consruction 2004” from the South African Chapter (GIGSA) of the International Geosynthetic Society.

A paper on this project was also accepted for presentation at the 8th International Conference on Geosynthetics which will be held between 18 and 22 September 2006 in Yokohama, Japan.

The motivation for the prestigious award follows:

Category:

Construction

Client:

Molatek Animal Feeds, A Division of Transvaal Suiker Beperk

Project:

Construction of 14 800m3 floating cover molasses storage reservoir

Project Team:

 

Consultant: 

Jarrod Ball & Associates (project leader: Riva Nortjι, resident engineer: Mzukisi Tshem),

Main contractor: 

Aquatan (project leader: Piet Meyer, contract manager: Sam LePhoto)

Earthworks contractor:

TransOos Konstruksie (project leader: Jim de Bruyn)

Civils contractor:

TSB Malelane Civils Department (project leader: Johnny Lugar)

Piping contractor: 

Bensy Engineering

TSB / Molatek Team:

Project Manager: Piet Hattingh

 

Principal Contractor (Molasses Reservoir):  Jaco Pretorius

 

Principal Contractor (Pumps and Piping):  Ingo Stark

The TSB Malelane and Komati Sugar Mills, situated in the Lowveld of Mpumalanga, generate molasses as a by product during the sugar cane crushing season, which is typically nine months. Molatek Animal Feeds uses the molasses generated by the mills as a raw material in the production of animal feeds, and requires molasses throughout the year in order to supply their markets. Storage of molasses during the crushing season for use during the off-season is therefore required. Both mills are equipped with steel tanks for molasses storage, and a 5 000m3 floating cover molasses storage reservoir was constructed at the Komati Mill in 1999. Insufficient molasses storage existed to provide for the molasses generated during the 2004 crushing season, and a number of alternative storage solutions were investigated, costed and compared by Molatek. The provision of a floating cover reservoir proved the most cost-effective, based on the initial costing exercise.

Jarrod Ball & Associates (JBA) was appointed to design the floating cover reservoir, as well as to provide specifications, contract documentation and drawings, site supervision and project management. Aquatan were appointed as the main contractor, to undertake the lining required. Following a tender process, TransOos Konstruksie were appointed to undertake the earthworks for the project, the TSB Malelane Civil Department was appointed to undertake the civil works, and Bensy Engineering was appointed to undertake the piping.

Given the high cost of storing molasses in road or rail tankers, the time frame during which the reservoir was to be designed and constructed was extremely tight. JBA were appointed in mid-April 2004, and the dam was commissioned for use in mid-September 2004, just less than five months after the project commenced. Both the design and construction of the project are worthy of note.

The construction of the reservoir is worthy of mention for the following reasons:
•               The reservoir was designed to hold 14 800m3, or approximately 20 000tons, at a specific gravity of 1.35. A 300mm freeboard has been allowed for foam. This is believed to be the largest molasses floating cover reservoir constructed in the southern hemisphere.
•               Construction of the dam took a total of 3 months.
•               The reservoir is lined with a Geocomposite Clay Liner and a 1.5mm thick HDPE geomembrane, while the cover comprises 1.14mm thick reinforced polypropylene. Construction therefore involved three different geosynthetics, providing the total lining and cover system for the reservoir. This is believed to be innovative for the storage of molasses.
•               Four contractors were involved in construction, the earthworks contractor, lining contractor, civils contractor and piping contractor, which required careful project management and good communication, given the relatively small area of the site.
•               Two unseasonal rain events caused a total of 9 days delay on the project, and the second event resulted in damage to the earthworks, which required rectification. The lining contractor made up time to allow for this.
•               The earthworks were completed to a very high standard, making installation of the lining easier.
•               More than 5 000m2 of GCL and 10 000m2 of geomembrane was placed in less than four weeks, to a high standard. This is particularly noteworthy given that the side slopes of the dam are at 1V:1.5H, and the cover material sheets are only 1.9m in width, so that considerable welding was required.
•               Design changes were made as late as three weeks before completion of construction, so as to meet programme and cost constraints as well as the client’s requirements, so that the construction team had to be flexible and adaptable.
•               No spreader pipes were installed during construction. Instead, the herringbone canal system on the floor was used to spread the molasses uniformly throughout the floor between the HDPE liner and R-fPP cover of the reservoir. Pipes are usually used to spread the molasses evenly across the floor, limiting stress on the cover. The first filling of the dam went smoothly, with the rate of filling low enough not to result in pulling or stressing the cover. This is believed to be innovative.
•               The inlet to the dam was constructed between the liner and the cover, so that no penetration of the liners was necessary for the inlet, limiting the risk of leakage. This is believed to be innovative.
•               The dam was constructed with an innovative set of weights and floats, developed taking the problems experienced with gas collection under the cover at the Komati molasses reservoir.  The floats, installed under the cover,run parallel across the width of the dam, allowing gas the shortest distance to escape. The weights are in place on the centre fold of the dam, so that stormwater will accumulate in this area, which can then be removed by the stormwater pump in position on the floating cover of the dam and so that gas is forced via the shortest route to the gas removal system around the perimeter of the dam. Installation of the floats and weights significantly complicated construction, but proceeded well.
•               The project’s BEE component was significant, with the resident engineer and the main contractor’s site manager being previously disadvantaged individuals, and the professional engineer and civil technician for the consultants, and the SHEQ representative and auditor on behalf of the client, being women. 

It is also worth noting that the project team worked well together, with the client’s representatives taking an active role in the project at every stage. Given that the new molasses floating cover reservoir is working well, and the dam was commissioned before the Mill’s existing storage structures had reached capacity, this project is considered a success.

2009 END

Liner Applications \ Technical Specs \ Typical Drawings \ Seaming Systems \ Applications
 Product Range : Geomembranes \ Geosynthetic Clay Liners \ Geo Drains \ Containers
Quality Assurance \ Contract History \ Company Profile \ Contact Us \ Disclaimer \
Home

Aquatan holds SABS ISO9001 2008 and IAGI Status

10 Diesel Road
PO Box 633
Isando 1600
South Africa

Telephone: +27 (0)11 974 5271
Fax:      +27 (0)11 974 4111
E-mail:    aqua@aquatan.com
GPS Coordinates: S 26° 08.504 E 28°12.155

All Contents Copyright © 2012 Aquatan (Pty) Ltd. | Webmaster: Celestine Ventures cc
 Date of entry: February 2004 | Latest Upload: 06 December, 2013

get_adobe_reader02